Swampscott Street Paving Schedule Announced

The work has started on Salem Street and will continue at other locations including Humphrey in the coming weeks.

Here are the streets scheduled for upcoming paving, according to a list from Swampscott Publi Works Director Gino Cresta.

Salem St Salem line to Humphrey
Aycliffe Rd Harrison Ave to Dead End Allen Rd Humphrey to Sumner Mostyn St Eulow to Beach Bluff Humphrey St Atlantic to Marblehead Line Cutting Rd Shephard Ave to Bradlee Ave Palmer Rd Atlantic to End Lewis Rd Kensington to Pleasant St Puritan Rd Woodbine to Winshaw Spring Ct Paradise to End Oakledge Rd Paradise to Swampscot Ave Plymouth Lane Plymouth Ave to End Bellear Dr Morningside to Sunset Duke St Stetson Ave to Nantucket Ave Alvin Rd Essex St to End Ryan Pl Essex To End

The town selected the most competive bidder for the summer and fall paving contract, DR Paving of Melrose, the Public Works director said.

DR bid $840,000 on the estimated $950,000 paving package, he said.

Find out what's happening in Swampscottwith free, real-time updates from Patch.

Under the contract the Melrose company will have 90 days to complete the work, he said.

This work is part of the town's regular road paving schedule and unrelated to the trench work by National Grid on the other end of Humphrey.

Find out what's happening in Swampscottwith free, real-time updates from Patch.


Get more local news delivered straight to your inbox. Sign up for free Patch newsletters and alerts.

We’ve removed the ability to reply as we work to make improvements. Learn more here